Greenwood is improving east-west connectivity and laying the groundwork for future growth and sustainability. The Worthsville Road project eases traffic congestion throughout the city and particularly downtown. 

Section 4a - COMPLETED

Interstate 65 to U.S. Highway 31

Section 4b - CURRENT

Collins Road (CR 250 E) to Griffith Road (CR 325)

Phase 2 of construction has begun between CR 300 E and Hurricane Creek. The segment will be closed for approximately 105 days. During this time, the intersection of CR 300 E will be open to traffic. Please pay attention to construction signage and detour routes in daily commutes, mapping your routes accordingly. View the detour map here.

Section 3 

U.S. Highway 31 to Averitt Road

  • Utility relocation efforts underway
  • Construction planned for 2020 and 2021 
  • View constructions plans for Section 3 here.

Section 2

Averitt Road to Honey Creek Road

  • Currently in the design phase
  • Construction planned for 2021

Section 1

  • Currently in planning phases